View text source at Wikipedia


Nawara Development Project

The Nawara Development Project is a landmark natural gas initiative located in Tunisia, representing a significant step in the country's energy development strategy. The project, situated in the south of Tunisia, focuses on extracting and processing natural gas from the Nawara gas field, a key resource in the country's hydrocarbon sector.

History

[edit]

The Nawara Development Project is a flagship natural gas initiative in Tunisia, aimed at tapping into the country’s hydrocarbon resources. Its history is marked by milestones in exploration, discovery, and infrastructure development:

Objectives

[edit]

Benefits

[edit]

Concept

[edit]

Status

[edit]

The Nawara Development Project progressed through various phases, with significant milestones achieved in financing, contracting, and construction. Below is a detailed status update:


Key Decisions and Financing

[edit]
  1. Final Investment Decision:
    • OMV made the final investment decision for the Nawara Development Project in March 2014.
  2. European Investment Bank Loan:
    • The European Investment Bank (EIB) agreed to co-finance the project with a loan of EUR 150 million to ETAP, signed in March 2014.

Engineering, Procurement, Construction & Commissioning (EPCC) Contracts

[edit]
  1. International Tender Process:
    • The recommendation for international tenders for the EPCC contracts for three work packages—Central Processing Facility (CPF), Pipeline, and Gas Treatment Plant (GTP)—was completed in 2014.
  2. Contract Signing and Engineering Work:
    • EPCC contracts were signed on August 18, 2014.
    • Contractors began engineering work, with feed endorsement certificates provided.

Pipeline Construction (370 km)

[edit]
  1. Right of Way (ROW):
    • State Land (200 km): Approval received for pipeline construction from Nawara to Kamour through Tataouine, with an estimated construction timeline of 10 months (completion expected by end of 2015).
    • Private Land in Gabès (28 km): 18 km cleared.
    • Collective Land: Negotiations with local stakeholders were ongoing as of the status update.
  2. Line Pipe Production:
    • The procurement contract for line pipe fabrication was awarded to Corinth Pipeworks.
    • Fabrication was 100% complete, and 35% of the pipes were delivered to Tunisia.
  3. Pipeline Valves:
    • The procurement contract for line valves was awarded to British LFF.

Gas Treatment Plant (GTP) Land Acquisition

[edit]
  1. Agreement and Compensation:
    • ETAP and local authorities in Gabès reached an agreement to compensate local farmers for land acquisition.
  2. Site Preparation:
    • Fencing and site grading were completed 100%.
    • The GTP site was handed over to the EPCC contractor.

Airstrip Development

[edit]
  1. Technical Evaluation:
    • The technical evaluation of tenders was finalized.
  2. Commercial Evaluation:
    • The commercial evaluation of tenders was ongoing.

Commercial Agreements

[edit]

In March 2014, key commercial agreements were signed with:


The Nawara Development Project's meticulous planning and structured execution reflect its significance as a cornerstone of Tunisia’s energy development efforts. These steps demonstrate the project's commitment to meeting technical, environmental, and economic objectives.

References

[edit]
[edit]